Project:
Design, Manufacturing, Installation and putting into operation of the reconstructed system for lifting and transporting dust with increased capacity of 40%
Realization of the project:
2011 year
Brief discription:
Design, Manufacturing, Installation and putting into operation of the reconstructed system for lifting and transporting dust with increased capacity of 40%, by:
- Increasing the capacity of the elevators on the line 1 and line 2
- Lead dust from the elevators
Realized activities:
- Complete replacement of drive unit
- Complete replacement of take up unit
- Manufacturing and replacement of buckets for elevators with increased volume
- Replacement of chains for elevators
- Reconstruction of unloading of dust
- Design and manufacture of dust transporters for increased capacity, with a central transport chain
- Assembly of the overall equipment
BOBOV DOL - Bulgaria
Production, supervision during installation and startup of pumps for transport of lime milk for the process of gas cleaning in the thermal power plant Bobov Dol-Bulgaria.
Contact Information
Str. Pero Nakov bb,
1000 Skopje,
Republic of Macedonia
Tel:
+389 (0)2 254 98 17
+389 (0)2 254 98 18
Fax/tel:
+389 (0)2 254 98 33
+389 (0)2 254 98 34
Web: www.pumpi.com.mk
E-mail: info@pumpi.com.mk