BOBOV DOL - Bulgaria
Project:
Production, supervision during installation and startup of pumps for transport of lime milk for the process of gas cleaning in the thermal power plant Bobov Dol-Bulgaria.
Realization of the project:
2011 year
Brief discription:
The pumps are intended for transport of lime milk for the process of gas cleaning in the thermal power plant Bobov Dol-Bulgaria. On November 2011 a new pump station was built for process of gas cleaning where were installed 6 pump aggregates; type D 80-60-74/U, each with Installed Motor
Realized activities:
- Design and production of 6 pump units (Horizontal Double Inlet Split Case Pumps) with Capacity up to: Q=6000 [m3/h], H=25 [m], Pm=630 [kW], n=730 [rpm], U=6000 [V]
- Supervision during installation and commissioning
BOBOV DOL - Bulgaria
Production, supervision during installation and startup of pumps for transport of lime milk for the process of gas cleaning in the thermal power plant Bobov Dol-Bulgaria.
Contact Information
Str. Pero Nakov bb,
1000 Skopje,
Republic of Macedonia
Tel:
+389 (0)2 254 98 17
+389 (0)2 254 98 18
Fax/tel:
+389 (0)2 254 98 33
+389 (0)2 254 98 34
Web: www.pumpi.com.mk