Project:
Projection and manufacturing of pump station
Realization of the project:
2008 year
Brief discription:
Projection and manufacturing of pump station for transport of water from furnace for ferronickel melting to the cooling tower
Realized activities:
- Three pumps with characteristics Q=890 m³/h, P=90 kw with frequent regulation
- Pipeline with length of 600 m Ø=500
BOBOV DOL - Bulgaria
Production, supervision during installation and startup of pumps for transport of lime milk for the process of gas cleaning in the thermal power plant Bobov Dol-Bulgaria.