Refernce 1

Reference 2

Mittal Steel Zenica, Bosnia & Hercegovina

Project:

Capital refurbishment of steel factory “Mittal Steel” Bosnia and Herzegovina

Realization of the project:

2007 year

Brief discription:

Reparation of pumps for diferent kind of mediums, water treatment Equipment. Reparation of lubrication systems with maximum pressure up to 250 bar. Steel construction fabricated with welding of elements of hotrolled steel sheet. Cleaning, overhauling and testing of central lubrication system. Inspection, supply of parts, refurbishment, installation, testing, cold commissioning, start up, putting into operation and hot commissioning of pumps in gas cleaning system.

Realized activities:

  • Reparation and installation of 82 pumps
  • Production and installation of water treatment equipment
  • Reparation and installation of 10 lubrication systems
  • Installation of cooling tower
  • Design and manufacturing of steel constructions
  • Repair of the pumps, shutter armature, drive reducers and other equipment in PS- 8 and on the Spot No 3.
  • Repair of the pumps, shutter armature, drive reducers and other equipment in PS-2 and on the DOOR system VP-4.
  • Overhauling of the pumps and sealing armature needs to be done.

BOBOV DOL - Bulgaria

fair thumbnail

Production, supervision during installation and startup of pumps for transport of lime milk for the process of gas cleaning in the thermal power plant Bobov Dol-Bulgaria.

Contact Information

Str. Pero Nakov bb,
1000 Skopje,
Republic of Macedonia

Tel:
+389 (0)2 254 98 17
+389 (0)2 254 98 18

Fax/tel:
+389 (0)2 254 98 33
+389 (0)2 254 98 34

Web: www.pumpi.com.mk
E-mail: info@pumpi.com.mk


MZT PUMPI © 2012